|
 |
What is a mechanics’
lien claim? |
|
 |
Liens filed on private
property in Wyoming are
known as Mechanics’
Liens. When a lien is
filed with regard to
work performed on
privately owned
property, it attaches to
and encumbers the fee
simple ownership of
property. Liens can be
filed against oil, gas,
well, and mining
property. Architects and
engineers have lien
rights. |
|
 |
Who can file a
Mechanics’ Lien Claim? |
|
 |
A mechanics’ lien is
available in Wyoming to
any party who has a
contract either with the
owner or the general
contractor. With regard
to oil, gas or mining
property, lien rights
extend to third tier
subcontractors or
materialmen who contract
with a subcontractor so
long as the
subcontractor has a
contract with a general
contractor and that
general contractor has a
contract with the owner.
Architects and engineers
who furnish plans for a
building or improvement
are also entitled to a
lien. |
|
 |
Are pre-notices for a
Mechanics’ Lien Claim
required? |
|
 |
There are several notice
requirements required in
Wyoming that must be
strictly followed. Every
prime contractor or
subcontractor must give
an initial notice with
regard to a newly
constructed
single-family home. This
notice must be given
within 30 days and must
be received by the owner
or its agent. This
notice with regard to
residential property is
a condition to being
able to file a lien in
Wyoming.
On all types of
projects, the “right to
claim a lien” must be
provided to the prime
contractor no later than
60 days after the date
on which services or
materials are first
furnished. This notice
requirement pertains to
projects on which the
prime contractor’s
contract is valued at
$50,000.00 or more.
Thereafter, before the
actual filing of a lien,
all contractors,
subcontractors, and
material must give 10
days’ notice to an owner
of their intent to file
a lien essentially
stating the amount of
the lien claim and from
whom it is due. The 90
and 120 day time periods
begin to run from the
last day from when work
was performed or
materials furnished
under a contract or the
date the work was
substantially completed
or there was substantial
completion on the
contract to furnish
materials, whichever is
earlier. |
|
 |
When should a Mechanics’
Lien Claim be filed? |
|
 |
Mechanics’ liens on
private property
must be filed within
120 days of
the last date the lienor
provided materials or
services to the project.
Lower tier
subcontractors have
90 days. The
90 and 120 day time
periods begin to run
from the last day from
when work was performed
or materials furnished
under a contract or the
date the work was
substantially completed
or there was substantial
completion on the
contract to furnish
materials, whichever is
earlier. |
|
 |
How much does it cost to
file a Mechanics’ Lien
Claim? |
|
 |
LienItNow.com
prepares, files and
serves Wyoming
Mechanics’ Liens for a
fee of $250.00. |
|
 |
Do I need a written
contract? |
|
 |
No. Oral contracts are
sufficient. |
|
 |
How does filing a
Mechanics’ Lien Claim
help me get my money? |
|
 |
On a private project,
the mechanics’ lien
places an encumbrance on
the property that makes
it difficult to resell
or re-finance the
property without first
removing the lien. |
|
 |
What is a Stop Notice
and why should it be
filed? |
|
 |
LienItNow.com
prepares and serves
Wyoming Stop Notices for
a fee of $100.00.
A Stop Notice is a
notification that has
the ability to enhance
the effectiveness of a
mechanic’s lien. A Stop
Notice, or a notice to
withhold funds, is sent
to the company that is
financing or funding the
construction funds for a
project. Once that
company receives the
Stop Notice, that
company has notice that
it should withhold
sufficient money to
satisfy the stop notice
claim. The purpose of
the Stop Notice is to
provide the lender,
financiers or funders of
the construction project
notice that there is
money owed to a
contractor,
subcontractor or
supplier so that an
inquiry can be made as
to why that money is not
being paid. |
|
 |
What is an Amendment to
a Mechanics’ Lien Claim? |
|
 |
LienItNow.com
prepares, files and
serves Wyoming
Amendments to Mechanics’ Lien Claims for a fee of $225.00. Amendments to a
mechanics’ lien claim
are often needed when
something about the
claim changes. Common
changes to a lien claim
are increases or
reductions in the amount
due to the lienor, or a
change to the last date
of work. |
|
 |
When should a Discharge
of Mechanics’ Lien claim
be filed? |
|
 |
LienItNow.com
prepares, files and
serves Wyoming
Discharges of Mechanics’
Lien Claims for a fee of
$75.00. Once the lienor
has been paid the amount
contained in its lien
claim, or has come to an
agreement that requires
the lien claim to be
removed from the
property records, a
Discharge of Mechanics’
Lien Claim should be
filed. |
|
 |
How much does it cost to
file an Extension of a
Mechanics’ Lien Claim? |
|
 |
LienItNow.com
prepares, files and
serves extensions of
Mechanics’ Lien Claims
for a fee of $75.00.
All lien claims expire
after a certain period
of time, and filing an
extension of the
mechanics’ lien claim
prolongs the expiration
date. Wyoming law,
however, does not permit
an extension of
mechanics’ lien claims. |
|
 |
Can I file a Bond Claim
on the Project? |
|
 |
LienItNow.com
prepares, files and
serves Wyoming Bond Claims for a fee of $250.00. Bond claims
can only be filed on a
project where the owner,
contractor or
subcontractor has
obtained a payment bond
to ensure that every
contractor receives
payment for the work
performed on the
Project. The payment
bonds issued by sureties
for construction
projects have specific
timing requirements, but
most require claimants
to submit claims against
the bond within sixty to
ninety days from the
claimants’ last date of
work. Bond claims are as or
more effective than a
lien claim because the
payment bond acts as a
guarantee that payment
will be made for work
properly completed. |
|
 |
Do I need to file a
Pre-Notice to make a
claim against a payment
bond? |
|
 |
LienItNow.com
prepares, files and
serves Wyoming
Pre-Notices for bond
claims for a fee of
$50.00. Depending on
the terms of the payment
bond, pre-notices may or
may not be required.
LienItNow.com
recommends that, prior
to or immediately after
starting work or
delivering materials to
a project,
subcontractors and
suppliers, file a
pre-notice that it is a
potential beneficiary of
the construction
project’s bond. |
|
|
Click on the appropriate link below to start
the filing process in Wyoming.
Lien |
Discharge of Lien |
Pre-Lien
Notice | Stop
Notice |
Amendment of Lien |
Bond Claim
Copyright 2009 LienItNow
Copyright 2010
LienItNow.com
Use of this website is subject to: Legal
Disclaimer
Website Development
and Maintenance by:

|
LienItNow.com | 1-888-543-6765 |
|
Keywords: Lien, Construction Lien Public Construction
Lien, Residential Construction Lien, Commercial Construction
Lien, Residential Construction Lien, Public Construction
Lien, Mechanics Liens |
|